Needs a decision
158 SKUs outside policy in the next 90 days
DS-500 runs short in week 6, then piles up
Phase 3 · Dispenser refill, 500 ml at Oakville DC · next 90 days, from the last 26 weeks of demand
Projected on handWith suggested changesStock policy bandOpen PO receipt
Bring 600 cases forward from Dec 21 to Nov 30
Pull in · PO 31990
Keeps DS-500 above min through week 6. The India plant shows finished stock ready to ship.
Cut the Jan 4 order from 900 to 400 cases
Reduce · PO 32044
Avoids $61K of stock above max. Change before the supplier's Nov 20 cut-off.